CPCC Parking Lot Repair, Sealing, and Restriping
In August we are going to repair, sealcoat and restripe the church parking lot.
During the week of August 4 – 8, the north driveway from the street to about 50 ft in and the middle driveway from the street to about 8 ft in, will have the existing paving removed and replaced.
On August 12 and 13, one half of the parking lot will be sealed and restriped.
On August 19 and 20, the other half of the parking lot will be sealed and restriped.
At all times you will have access to all the buildings on the campus. For example, you may have to enter and exit the campus via the south driveway or access the preschool via room 4.
If you have any questions, please contact Dave Wierenga.
Stage Two August 19-20
Stage One August 12-13